THAPPLINE_INSTALL THE AC MITIGATION SYSTEM AT PIPELINE LAM LUK KA TO DON MUENG (KP 24 + 800 - KP 26 + 800)

install AC mitigation systems
Installing the Zinc Ribbon Anode along the pipeline by embedding the Zinc Ribbon one meter deep and aligning between the power transmission lines and pipelines with both filling and grinding by sand 0.5 meters. And placing PVC Warming Strip size 200 millimeter throughout the excavation, with the following details:
  • Area 1 KP.24 + 800 – KP.25 + 025 Distance 255 meters
  • Area 2 KP.25 + 050 – KP.25 + 660 Distance 610 meters
  • Area 3 KP.25 + 700 – KP.26 + 800 Distance 1100 meters
  • The connection between the pipeline and the zinc ribbon must be connected in the 7 test station with the Soil-State Decoupler device of 2.0 kA. Installing zinc ribbon anode standards for zinc ground mat at under 7 test station. In case of having to connect from the pipeline to test station, use Pin Brazing method only.
Description

Thai Petroleum Pipeline Co., Ltd. (Thappline) intends to hire the AC MITIGATION system installation at Lam Luk Ka - Don Mueang pipeline (KP.24+800 – KP.26+800) to prevent the damage from the high voltage of power transmission lines. That affects oil pipelines and workers.

Details

  • Owner: Thai Petroleum Pipeline Co., Ltd. (Thappline)
  • Contractor: CGL Engineering Co., Ltd
  • Loation: Pipeline Lam Luk Ka - Don Mueang (KP.24+800–KP.26+800)
  • Working Period: 180 days